Elaf Residence
Main video
Engineering Report
Detected changes
Completion of the concrete structure for typical floors up to the roof annex, with external red brick masonry work visible on the upper floors.
Commencement of internal wall plastering in several units, with sand and cement supplies staged on-site.
Installation of preliminary electrical boxes and conduits within the walls prior to the final plastering stage.
Facades covered with green safety netting and scaffolding remaining in place around the entire building.
Progress reading
The visual evidence aligns with the concrete completion rate (45%), as the structure is structurally complete, while the electrical and plumbing progress (20%) reflects the initial rough-in stages visible in the interior photos. The stability of the percentages compared to the previous visit suggests that work is currently focused on internal details that do not significantly increase the overall completion rates at this stage.
vs previous visit
Compared to the photos from the previous visit (21-26), a slight progress is noted in the brickwork on the upper floors, along with an increase in the volume of internal material stockpiles for plastering works, despite the percentages recorded in the report remaining constant.
Expected next milestones
Completion of internal plastering works, commencement of roof insulation, and start of external facade installations.