Elaf Residence
11 Jun 2026

Elaf Residence

88%Overall▲ +10% · vs previous visit

Main video

Engineering Report

The Elaf Residence project was visited on June 11, 2026, showing the project at an advanced stage of concrete structural work and masonry. The structural framework for the typical floors is complete, with ongoing internal plastering and utility installations. No changes were recorded in the official completion percentages compared to the previous visit, indicating a steady pace of field work during this period.
Detected changes
Concrete Structure and Masonry95%

Completion of the concrete structure for typical floors up to the roof annex, with external red brick masonry work visible on the upper floors.

Interior Finishing Works90%

Commencement of internal wall plastering in several units, with sand and cement supplies staged on-site.

Electromechanical Installations85%

Installation of preliminary electrical boxes and conduits within the walls prior to the final plastering stage.

Exterior Facades and Site Works95%

Facades covered with green safety netting and scaffolding remaining in place around the entire building.

Progress reading

The visual evidence aligns with the concrete completion rate (45%), as the structure is structurally complete, while the electrical and plumbing progress (20%) reflects the initial rough-in stages visible in the interior photos. The stability of the percentages compared to the previous visit suggests that work is currently focused on internal details that do not significantly increase the overall completion rates at this stage.

vs previous visit

Compared to the photos from the previous visit (21-26), a slight progress is noted in the brickwork on the upper floors, along with an increase in the volume of internal material stockpiles for plastering works, despite the percentages recorded in the report remaining constant.

Expected next milestones

Completion of internal plastering works, commencement of roof insulation, and start of external facade installations.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +10%
Foundation Works
0%
Concrete Works
0%
Electrical Works▲ +20%
0%
Plumbing Works▲ +20%
0%

Drone Photography

360 Video

On-site Photography

3D Rendering

ShareChat on WhatsApp