Elaf Residence
Main video
Engineering Report
Detected changes
Completion of exterior plastering for most facades with scaffolding and safety netting still in place, and the commencement of aluminum window frame installation on certain floors.
Execution of interior plastering and floor tiling in several apartments, with electrical boxes and initial wiring installations visible.
Installation of suspended sewage pipes and water supply lines, along with the laying of electrical cable trays.
Implementation of waterproofing and thermal insulation for the roof, with ongoing work on elevator machine rooms and upper water tanks.
Progress reading
The visual evidence aligns with the reported completion rates; images (14, 18) reflect the 70% progress in electrical works through visible internal wiring, while plumbing works (image 13) are in the main piping stage, justifying the 55% completion rate.
vs previous visit
Compared to the photos from the previous visit (21-26), we observe the transition of work from the pure structural phase to the advanced finishing stage, as most architectural openings have been closed, interior painting has commenced, and window frames have been installed.
Expected next milestones
Completion of window glass installation, commencement of final painting works, and installation of final sanitary and electrical units.