Elaf Residence
Main video
Engineering Report
Detected changes
Completion of column and slab pouring up to the fifth floor, with internal concrete stairs visible and reinforcement steel ready for some upper elements.
Commencement of wall construction using red clay bricks and cement blocks on the ground and first floors, with additional brick stocks stored on-site.
Installation of electrical conduits (orange PVC pipes) within slabs and walls, with plumbing pipes delivered on-site in preparation for installation.
The site is enclosed with safety fencing, with excavation equipment (excavators) operating in the adjacent plot or within the general site perimeter, and a stock of bagged cement available.
Progress reading
Visual observations align with the reported completion rates; the structure reaching the fifth floor reflects the 45% completion in concrete works, while the start of electrical and plumbing rough-ins within the newly built walls accounts for the 20% progress recorded for those sectors.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of the final floor roof casting, expansion of masonry work for the upper floors, and commencement of plastering for the finished walls.