Elaf Residence
6 Apr 2026

Elaf Residence

70%Overall▲ +14% · vs previous visit

Main video

Engineering Report

The concrete structure has been 100% completed, with significant progress in masonry work (red brick) on the upper floors and parapets. Internal plastering has commenced in several units, while external facades remain covered with safety netting as service infrastructure installations continue.
Detected changes
Concrete Structure100%

Completion of pouring all structural elements, including the final floor slab and roof structures (parapet).

Masonry Works95%

Completion of external red brick wall construction for typical floors and commencement of roof parapet masonry.

Interior Finishes90%

Commencement of internal wall plastering works on several floors and preparation of openings.

Exterior Facades100%

Installation of metal scaffolding and green safety netting around the building perimeter to begin exterior cladding works.

Progress reading

The 100% completion of the concrete structure is consistent with the images showing the conclusion of all pouring works. Electrical and plumbing works (45% and 36% respectively) are evident through the initial rough-ins within the walls prior to plastering. The slight adjustment in the plumbing percentage may be attributed to a reassessment of work items or the replacement of previous installations.

vs previous visit

Compared to the previous visit, the project has progressed from the final column and slab casting stage to advanced masonry work and facade scaffolding. There is also clear evidence of internal plastering works, which were not present previously.

Expected next milestones

Completion of internal plastering works, commencement of metal/wooden door frame installation, and the start of building facade works.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +14%
Foundation Works▲ +40%
0%
Concrete Works▲ +15%
0%
Electrical Works▲ +5%
0%
Plumbing Works-4%
0%

Drone Photography

360 Video

On-site Photography

3D Rendering

ShareChat on WhatsApp