Elaf Residence
6 Apr 2026

Elaf Residence

78%Overall▲ +22% · vs previous visit

Main video

Engineering Report

The report indicates ongoing progress at the Elaf Residence project, with a focus on masonry work and initial interior finishes. The concrete structure is structurally complete for the typical floors and the annex, with significant progress in external and internal wall construction using red and cement bricks, and the commencement of interior plastering in certain areas.
Detected changes
Concrete Structure95%

Completion of column and slab pouring for typical floors up to the roof annex slab, with external scaffolding remaining in place to support complementary works.

Masonry Works90%

Significant progress in external wall construction using red bricks, and internal partitions using cement blocks. Photos show the completion of most typical floors and the commencement of work on the roof parapet and annex.

Interior Finishes85%

Commencement of internal wall plastering in some apartments, along with the installation of initial electrical conduits within the walls.

General Site and Facades90%

Facades are covered with green safety netting, with construction material stockpiles (sand and bricks) located in the immediate vicinity of the building and within the floors.

Progress reading

The visual evidence aligns with the reported completion rates (45% for concrete), as the structural skeleton is nearly finished. Electrical and plumbing works (20%) are in their early stages, visible through initial piping within the newly built walls. The lack of percentage variance compared to the previous visit suggests that current work is concentrated on internal details that have not yet resulted in a radical change to the overall figures.

vs previous visit

Compared to images from the previous visit, there is a noticeable increase in the density of masonry work on the upper floors (annex and roof) and the commencement of interior plastering work that was not previously visible. This indicates a shift in operational focus from the structural framework to the initial finishing stages.

Expected next milestones

Completion of masonry work for the annex, commencement of exterior plastering, and intensification of internal plumbing and electrical service installations.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +21%
Foundation Works▲ +40%
0%
Concrete Works▲ +15%
0%
Electrical Works▲ +20%
0%
Plumbing Works▲ +10%
0%