Elaf Residence
Main video
Engineering Report
Detected changes
Completion of column and slab casting for typical floors up to the roof annex, with the structural frame appearing complete in most sections.
Significant progress in wall construction using red clay and cement bricks across various floors, including the completion of the roof parapet.
Commencement of laying electrical conduits and pipes, and installing junction boxes within the newly built walls.
Execution of initial water supply and drainage piping within architectural spaces and preparation of vertical pipe shafts.
Continued presence of external scaffolding and green safety netting around the entire building, with the general site remaining in the construction storage phase.
Progress reading
The visual evidence aligns with the reported completion rates (45% for concrete work and 20% for plumbing and electrical), clearly showing the operational shift from the concrete structure to the internal partitioning and service infrastructure stages.
vs previous visit
Compared to the previous site visit photos, the completion of internal and external wall construction is noted across additional floors, along with an increased density of visible electromechanical installations within the rooms.
Expected next milestones
Completion of internal plastering works, commencement of waterproofing for bathrooms and kitchens, and the start of external building facade works.