Elaf Residence
25 Nov 2025

Elaf Residence

45%Overall▲ +9% · vs previous visit

Main video

Engineering Report

The Elaf Residence project site was visited on November 25, 2025, where the project is shown to be in an advanced stage of structural and masonry work. Most concrete slabs for the typical floors have been poured, while red brick wall construction continues across various levels, and initial rough-ins for internal electromechanical installations have commenced.
Detected changes
Concrete Structure95%

Completion of casting columns and slabs for typical floors up to the roof annex, with formwork removal noted across most levels.

Masonry Works90%

Significant progress in external and internal wall construction using red bricks, with masonry work reaching the upper floors.

Electrical and Plumbing Works85%

Commencement of electrical conduit installation within walls, setting up distribution points and switch boxes, along with plumbing drainage rough-ins.

Site Infrastructure and Safety90%

Installation of green safety netting on the building facades and organization of construction materials in the surrounding perimeter.

Progress reading

The visual observations align with the concrete completion rate (45%), as the structural framework is nearly finished. Electrical and plumbing works (20%) are clearly visible in the interior photos through the initial piping installed in the walls prior to plastering.

vs previous visit

Compared to the photos from the previous visit (Photos 21 to 26), the project shows a transition from the final ceiling pouring stage using concrete pumps to the completed 'skeleton' stage and the commencement of internal partitioning and technical installations. This reflects progress in the quality of executed works despite the consistency of the percentages recorded in the report.

Expected next milestones

Completion of masonry work for the annex, commencement of internal plastering, and installation of door and window frames.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +9%
Foundation Works▲ +15%
0%
Concrete Works▲ +10%
0%
Electrical Works
0%
Plumbing Works▲ +10%
0%