Elaf Residence
Main video
Engineering Report
Detected changes
Completion of casting columns and slabs for typical floors up to the roof annex, with formwork removal noted across most levels.
Significant progress in external and internal wall construction using red bricks, with masonry work reaching the upper floors.
Commencement of electrical conduit installation within walls, setting up distribution points and switch boxes, along with plumbing drainage rough-ins.
Installation of green safety netting on the building facades and organization of construction materials in the surrounding perimeter.
Progress reading
The visual observations align with the concrete completion rate (45%), as the structural framework is nearly finished. Electrical and plumbing works (20%) are clearly visible in the interior photos through the initial piping installed in the walls prior to plastering.
vs previous visit
Compared to the photos from the previous visit (Photos 21 to 26), the project shows a transition from the final ceiling pouring stage using concrete pumps to the completed 'skeleton' stage and the commencement of internal partitioning and technical installations. This reflects progress in the quality of executed works despite the consistency of the percentages recorded in the report.
Expected next milestones
Completion of masonry work for the annex, commencement of internal plastering, and installation of door and window frames.